Ethiopians contribute $460 million to Renaissance Dam

30 Aug 2017

The Ethiopian National Council for the Coordination of Public Participation on the Construction of the Grand Ethiopian Renaissance Dam (GERD) said Ethiopians have so far contributed around $460 million towards the construction of the Dam, through various schemes including bond sales, athletic events and lottery draws.

Of the total, $4.9 million was from Ethiopians and foreign nationals of Ethiopian origin in the diaspora.

Construction of the $4.7 billion dam began in April 2011 and it is now 60% complete. When fully operational, it will generate up to 6,450MW of electricity. Preparations are underway to install two 375MW turbines for test power.

The dam is funded solely by domestic funds (from Ethiopians and foreign nationals of Ethiopian origin) and has been billed as a landmark project signalling Ethiopia’s renaissance.

…power lines ready for transmission

Ethiopian Electric Power announced that 500kV high power transmission lines and distribution stations are in place, ready to carry electric power when the GERD starts generating.

Over 28 billion Birr was expended on the construction of the power distribution stations.

Diaspora
Prev Article Next Article

Latest News

Browse all
Here we take a look back at 2017’s highlights, month by month, and what we are looking forward to in 2018.
16 Jan 2018
2017: Year in Review
The weekly publication from the Ministry of Foreign Affairs in Ethiopia.
12 Jan 2018
A Week in the Horn
For more than two decades, the Ethiopian government has been striving to achieve the socio-economic transformation of the country. The vision to ensure all-inclusive growth and to attain lower middle-income status by 2025 continues to be anchored on executing policies aimed at the overall eradication of poverty through comprehensive development. This vision can also be realized through the utilization of…
9 Jan 2018
Cooperation on The Nile, Essential for Mutual Benefits
The Ethio-Djibouti railway line has started commercial operations for passengers and freight. The railway, which is Sub-Saharan Africa’s first electrified railway, connects Ethiopia’s capital Addis Ababa with the port of Djibouti. Travel time will be cut from around 3 days to 10 hours.
8 Jan 2018
All Aboard! Africa’s first electrified railway from Addis to Djibouti begins commercial operations
The weekly newsletter from the Ministry of Foreign Affairs in Ethiopia.
5 Jan 2018
A Week in the Horn
Japanese casualwear retailer, Uniqlo, will open its  first African manufacturing plant in Ethiopia, joining fashion giants such as H&M and Calvin Klein, who are already manufacturing in Ethiopia.
4 Jan 2018
Uniqlo to open first African manufacturing plant in Ethiopia
At this New Year, my wife, Abebetch Zeleke Aweke, and all Embassy staff, join me in wishing the people and government of the United Kingdom our heart-felt best wishes for the year ahead.
2 Jan 2018
New Year Message from the Ambassador
Ethiopia’s historic walled city of Harar was named the top place to visit in National Geographic Traveler magazine’s annual list of 21 must-see destinations to visit in 2018. Discover the “most surprising city in East Africa”, boasting 82 mosques, as well as Ethiopia’s best beer and highest quality coffee.
29 Dec 2017
Harar named National Geographic’s best place to visit in 2018
The weekly newsletter from the Ministry of Foreign Affairs in Ethiopia.
29 Dec 2017
A Week in the Horn
Ethiopian Electric Power has signed two agreements worth $4 billion, to build two geothermal power plants, to be run by the country’s first privately-owned utility. The two plants - Corbetti and Tulu Moye - will produce a combined 1,000MW of power upon completion in eight years’ time.
27 Dec 2017
Two new geothermal power plants to be built
The weekly newsletter from the Ministry of Foreign Affairs in Ethiopia.
15 Dec 2017
A Week in the Horn